3.01.1
Public Transit Planning by CCTA http://www.cctaride.org/
[Staff Manager: Peter Keating]
3.01.11 Ridecheck – 20% Complete
·
Continued Special surveys of Ledgewood and
South Meadows Ridership
3.01.12 System-wide
Time Point Analysis – 14% Completed
·
Surveying routes with problem on time performance.
3.01.13 Rider
Surveys – 20% Complete
·
Completed Montpelier Link Rider Surveys on
departure time potential change
·
Conducting survey of Essex Junction
Ridership
3.01.14 Service and Operations
Planning - 25% complete
·
Proposed changes to Ledgewood and South Meadows Routes,
a new Pine St Route
·
Proposed new Lakeside Commuter Route
·
Reported on departure time change to Montpelier Link
·
Planning/ Permitting/Lease Agreements for St. Albans Link
·
Working with Chittenden County Elderly and Disabled
Transportation Committee on FY 05 year end inter-regional funding transfers and
FY06 local agreements.
3.01.15 ITS
Applications – 10 % Complete
·
Working on signal priority coordination w/MPO and VTrans
·
Working on project for ITS signage at Cherry Street
3.01.16 Passenger Shelters – 25 % Complete
·
Planning FY 06 Shelters
3.01.17 Market Research
and Data Collection - 0% Complete
·
Collected
demographics to analyze departure/arrival time of St. Albans Link Express
3.01.18 Bus Stop and Route
Variation Database Maintenance and Tracking – 0%
Complete
·
No work planned or undertaken.
3.01.19 Vehicle Type Operating Cost Comparison – 12% Complete
·
Collecting data on bus maintenance
and operating expanses by bus size
3.01.20 Maintenance and Facility Planning - 30% Complete
·
Completed permitting for CCTA bus
storage expansion
·
Working with Winooski on Multimodal
Grant application
·
Working the Burlington on Transit Center and Intercept Parking Facilities
3.01.21 Financial Planning – 15% complete
·
Working on FY06 Capital programming
3.01.22 Regional Public Transportation Expansion - 0% Complete
·
No work planned or undertaken.
3.01.2 Public Transit
Planning by CCMPO & Human Services Transportation Analysis– 15% Complete http://ccmpo.org/ptp/index.html [Staff Manager: Peter Keating]
·
Unmet
Needs survey distributed to 40 plus social service agencies and transportation
providers.
3.02 Environmental
Planning – 0% Complete [Staff Manager: Christine Forde]
·
No
activity this period.
3.02.1 10% Challenge - 17%
Complete http://www.10percentchallenge.org [Staff Manager: Christine Forde]
Primary Products:
1.
Participate and assist in
coordination of activities and events (Way-to-Go Week and Best Workplaces for
Commuters, Earth month events at institutions and businesses) to promote use of
transportation alternatives and energy conservation.
·
Way2Go—no progress this reporting
period
·
Channel 17 show on transportation
alternatives, promotion of CCTA, no-idling and discussion between land use and
transportation, climate change/air quality.
·
ACA Board meeting prep for Sept 2nd
board meeting.
2.
Work with and support
Chittenden County communities on energy reduction programs including supporting
use of alternative forms of transportation to single occupant vehicles--Seek
supplemental resources to support local planning and implementation for clean
air and promotion of higher occupancy vehicles and increased transit use.
Specific activities include student research projects, employee energy
challenge program developed and piloted, and participation in Vermont Clean Vehicles
Coalition meetings including project planning and development for outside
funding.
·
Meeting with TDM partners to
review final TDM report. Comments provided to CCMPO for suggested changes to
TDM final report.
·
Suggested list of strategies
developed by sector provided to City of Burlington to move the City to the next
level regarding achievement of target goals for GHG reductions by 2010.
·
Collaboration with Vermont Natural
Resources Council, Sustainable Energy Resource Group and Alliance for Climate
Action in development of letter of interest for major two-year Cox Foundation
grant to help form energy committees in communities, to assemble a starter-kit
for use by communities/groups, and to help transfer the 10% Challenge program.
Full $150K proposal requested by Cox, due October 15th.
3.
Collaborate with and advance
no idling initiatives and other clean air initiatives in Chittenden County communities and schools with partners including American Lung Association of Vermont,
Vermont Department of Health, Champlain Initiative, Agency of Natural Resources
and others.
·
Promoted anti-idling campaign on
Channel 17 and sent out information packets and signs to area businesses.
4.
Education, outreach, and
public participation: Raise awareness of planners, decision-makers and the
public via workshops/presentations, brown bag lunches, newsletter articles
including case studies, success stories and lessons learned.
·
Participated in brainstorming
meeting with Burlington City department heads/Mayor regarding suggested next
steps for actions to reduce air pollution and greenhouse gasses.
·
Coordinated Channel 17 Live at 5:25 discussion on air quality, climate change and actions individuals can take to reduce
emissions from vehicles.
·
August 2005 eMission newsletter
published and distributed.
3.03 Bicycle/Pedestrian
Transportation Planning – 5% Complete [Staff Manager: Peter Keating] http://www.ccmpo.org/BikePed/
·
No
work undertaken.
3.03.1 Safe Routes to
Schools (SR2S) Pilot Projects - 15% Complete [Staff
Manager: Peter Keating] http://www.ccmpo.org/SR2S/
·
Met
with stakeholders to discuss emphasis areas for the coming school year and
methods to inform the public about the program.
·
Met
with VTrans staff to discuss implications of the new federal Safe Routes
program.
·
Assembled
PowerPoint for conference presentations this fall.
3.04.1 2025 Metropolitan
Transportation Plan Implementation (MTP) – 0% Complete
[Staff Manager: Peter Keating] http://www.ccmpo.org/MTP/
·
No
work planned or undertaken.
3.04.2 2030 Metropolitan
Transportation Plan (MTP) - 5% Complete [Staff Manager: Peter Keating]
·
Scope
of work and project schedule posted on web.
·
Project
advisory committee operating procedures drafted for Board consideration.
·
The
consultant met with staff member Peter Keating to review the MTP Advisory
Committee makeup and overall MTP public involvement effort in light of new
federal legislation. She reviewed and made recommendations for revisions to
the Advisory Committee’s procedures
3.06 Transportation
Demand Management (TDM) Program – 15% Complete [Staff Manager: Peter Keating]
·
TDM Partners
met and formulated final comments to draft Plan. Comments sent to consultant
3.07 Route 15 Corridor Land Use/Transportation Plan – 0% Complete [Staff Manager: None]
·
.The
Scope of Work is being developed by the four municipalities in the corridor.
.
3.09 Transportation Systems Management - 18% Complete [Staff
Manager: Susan Smichenko].
3.11 Development Review
– 10% Complete [Staff
Manager: Susan Smichenko]
●
Staff
answered questions from the coordinator at the District Environmental
Commission.
3.13 Freight Transportation Planning - 5% Complete [Staff
Manager: Daryl Benoit]
http://www.ccmpo.org/freight/
·
Held
meetings with NECR & Rail America about employing Transload (rail to truck)
in Chittenden County as well as possibilities of shifting the Burlington
Railyard from its current location, under SAFTEA-LU provisions. Further
strategy is dependent on outcome of the legislative summer study on H.542,
which proposes the formation of a Vermont Rail Authority.
·
Received
mandate from VTrans to undertake a TPI-work task, identifying and inventorying
marketable and developable property adjacent to railroad ROW for Chittenden County. Preliminary steps will be to involve participation of CCRPC & GBIC. A project timeline will be completed in September 2005.
·
NECR
Vice President Charlie Moore appeared at the August Board meeting. He stated
interest in working with the MPO to upgrade the Burlington to Essex rail-line
to run local commuter and Amtrak services, as well as develop bikeways within
this rail corridor.
3.14 Route 2 Corridor Study – 15% Complete [Staff Manager: Susan Smichenko]
·
Seven
responses were received for the RFQ
·
Staff
reviewed and ranked submissions in preparation for the September meeting
planned with the Review Committee to short list consultants.
·
The public
outreach consultant reviewed RFQs in preparation for a Stakeholders' Meeting on
September 7, 2005.
3.16 Route 7 Circulation Study - 15% Complete [Staff
Manager: Susan Smichenko)]
·
Consultant
working on existing conditions report for the project area.