In the mid nineties communities along the Burlington to Essex Rail
Corridor requested that the Vermont Agency of Transportation (VTrans)
consider the expansion of the Charlotte to Burlington rail commuter
service to Essex Junction.
| In 1998 and 1999 and in response to this request, the Vermont
Congressional Delegation supported the initiative by requesting
and then receiving authorization of $6,968,928 in federal funding
in two Congressional Earmarks. |
| VTrans was the grantee for the project and asked the Chittenden
County Metropolitan Planning Organization (CCMPO) to facilitate
the project in collaboration with VTrans in 1998. |
| The Vermont Congressional Delegation, through a request from the
State of Vermont, sought and received two extensions from Congress
on this project to September 30, 2002. |
| CCMPO, at a cost of $360,000, undertook a Rail Feasibility Study
in 1998-99 of the rail corridor and determined that the extension
of the Charlotte to Burlington commuter rail service into Essex
Junction was feasible. |
| The federal criteria were revised in 1999 to require an Alternative
Analysis of the Burlington to Essex Junction commuter rail project
and VTrans contracted with FTA for an Alternative Analysis in March
2000 at a cost of $2.1 million ($1.7 million federal and $400,000
state). |
| In the fall of 2000, CCMPO allocated $750,000 for Phase 1A of
the Alternative Analysis, developed a Scope of Work and Procurement
Process, and hired a consultant. |
| In the spring of 2001, the consultant undertook an Alternatives
Analysis of the Corridor that is based upon the existing transportation
system and all projects currently in the adopted Transportation
Improvement Program. These include such major projects as segments
A and B of the Circumferential Highway, Kennedy Drive, Shelburne
Road, Lime Kiln Bridge, the Southern Connector, and Riverside Avenue.
|
| In September 2001, CCMPO approved the analysis of the consultant.
They concluded that the best approach to solving the problems in
the Route 15 Corridor was a multimodal solution that included commuter
rail, feeder bus service, and minor improvements on Route 15, such
as turning lanes and new traffic signals. |
| In the summer of 2001, the consultant was given approval to proceed
to complete Phase 1B to prepare an Environmental Assessment, undertake
a financial and institutional study, determine more detailed costs
for the improvements, and study Transit Oriented Development around
the train stations. |
| In February 2002, CCMPO added the Route 15 Corridor Plan to the
Long Range Transportation Plan. |
| In the winter of 2002, CCMPO continued to detail the multimodal
transportation plan for the Route 15 Corridor and added a proposed
bike/ped path between downtown Essex Junction and Lime Kiln Road,
traffic signal optimization and the use of new technology in the
highway corridor to improve traffic flow. |
| In June 2002, the Draft Environmental Assessment of the commuter
rail was completed. |